|
| |
Excavation for the Tire Bale Home
by Leonard Jones, P.E.
Preparing for Excavation:
- Determine the location of the building on the ground and mark it with
wooden stakes at the corners. Make sure you measure across the diagonals to
make sure that the building will be square. Put in some "offset" stakes so
you'll be able re-locate the corners after excavation. Also mark out the
locations of the front, middle and rear E-W tire walls.
- Next, determine the above ground elevation of the front wall tire bales
from the plans and set a stake with its top at that elevation.
- Then, rent or borrow a contractor's level and leveling rod and set a
temporary bench mark far enough away from the construction area so it won't
be disturbed. This elevation will arbitrarily be called 100.00 ft. All
other elevations will be set as plus or minus from this elevation. (see
sketch)
- Next, from the plans, determine the elevations of the rough floor for
both levels.
- Now lay out a 10' grid on the ground with wooden stakes and - using the
contractor's level, determine the elevation of the ground at each grid
point. Subtracting the rough floor elevation or the front wall bottom tire
bale elevation from the ground elevation will tell you how much soil must be
removed at that point to get down to the elevation you need... Mark this
amount on the respective stake for the machine operator's use. Be sure to
extend the excavation 3-4 feet beyond the outside of the tire walls so that
there will be room to install the vapor barriers and drain pipe.
- Finally, again using the contractor's level, determine the point in
front of the building where the bottom front wall tire bale elevations
intercepts ground elevation. This is the front limit of excavation.
Excavation:
- Start with the upper level and have the operator excavate down to rough
floor elevation for that level. Extend this excavation out to where it
intersects with ground level. He will probably have to cut a small access
way in the side of the excavation to get his machine in and out of this
level... After he gets this area cut down level, have him ditch around the
sides and back to accomodate the drain pipe per the drawing. In the areas
where the tirebales will sit, he should cut the earth down as close as
possible to the elevation where they will sit.
- Now have him excavate the "shelf" at the rough floor elevation of the
lower level. Same process as the upper level, except you don't need to
accommodate a drainage pipe in back of the middle wall. Be sure to have him
cut down to grade for the area where the tire bales will sit.
- Now have him excavate in the front wall area at the elevation of the
bottom of the front wall tire bales. Extend this excavation out to daylight
sloping slightly downward for drainage...
- He'll probably have to do some clean-up digging to get the sidewall tire
bale areas right.
- Finally, there's other misc. digging to be done. Ditches for drain
pipes, water, electrical, septic tank, etc. need to be dug at this point.
Final Site Layout:
- Using the offset stakes, re-locate and re-stake the building corners.
Double-check the corner-to-corner dimensions to make sure they're OK...
Also double-check across the diagonals (REALLY IMPORTANT!!!) to make sure
that the final layout is square.
- Erect a batter board (see diagram) at each side of each tire wall - far
enough out to not get disturbed while you're setting the tire bales...
Pound in the vertical stakes, then level the horizontal piece front-to-back
at the elevation where the top of the first course of tire bales is supposed
to go. You'll probably need the contractor's level again!! Use clamps to
hold the horizontal piece to the verticals to start with - then, when you
have it set exactly - attach it with construction screws. When you have the
batter boards set for the front wall, stretch a string line TIGHT across the
top of the horizontal piece - making sure that it goes exactly over the top
of the corner stakes... Clamp the string to the batter board, then use a
plumb bob to check that it's over the top of the corner stake. When you
have it located properly, drive small nails or construction screws into the
top of the horizontal. piece to permanently locate each string line...
(this will let you take the string down and put it back up in the same place
whenever you need to during the job. Start with the front wall and work
your way to the back. The front string line is the baseline for the entire
building layout, so it has to be EXACTLY right... See any good carpentry
book for detailed instructions on batter boards...!!
- Now erect batter boards for the east and west walls. This is the same
as described above, except that the string lines attached to these batter
boards will not be level front to back. These will be used primarily for
alignment of the E and W walls and for final location of the building
corners. Once you have this done, check EVERYTHING again - especially
across the diagonals of the building.
- Once you have completed this, you should be able to locate everything in
the building using offset distances from the string lines... ...And you
should be ready to start placing tire bales...
Additional Considerations:
- Don't worry too much about the exact location of the drain pipe around
the building. Just make sure that it is below the bottom of the bottom of
the tire wall in back of the building, that it stays below the tire wall as
it continues around the sides, and that it is ALWAYS sloping downhill to
daylight - or to a "dry well" if the slope, etc. won't let you get out to
daylight...
- Excavation is a very inexact art... A good backhoe operator can get to
about +/- an inch of the desired grade under good conditions. If everything
turns out exactly right, your project will qualify for a "then a Miracle
happened" award. Most of the time you will be left with some additional
hand excavation or hand backfilling to get things to the exact grade you
need... (like where the tire walls will be located!!) Depending on the
situation, one or the other may be easier... Decide which up front and shed
no tears while you're pushing the shovel and/or wheelbarrow...
- If you decide to over-excavate a bit and backfill where necessary, it's
usually easier to backfill with sand or small gravel. It's easier to level
up than typical soil - it doesn't have large rocks in it, and it compacts
easily... You'll need sand and/or gravel anyway - so just figure in a
couple yards extra for misc. backfill when you order it...
- Give some thought - before your operator starts digging to where you
want the extra dirt (spoil) located. You can save yourself a lot of time,
effort, and cost by putting this stuff in the right place. Remember that
you will need some of it (but not all!) for backfilling, leveling, etc. And
maybe some more for berming around the outside of the house... Also
remember (IMPORTANT) that it's a lot easier to push a wheelbarrow downhill
than uphill.
Diagram:
To email us click
the bird.
Back to
Tire Bale Page
Back to
Tire Page 1
Back to
Homepage
For our Tire-House
story and more tire-house links: click
here
|